Programme record
Digital52°28′48″N 001°54′09″W

Eastern Fibre Spine

186 km of new duct and 1,900 km of fibre connecting 214 public sites — schools, libraries, GP surgeries and council offices — onto a single managed telemetry and monitoring platform.

Client
Combined authority
Contract value
£9.6m
Duration
11 months
Programme
2024 — 2025
Project scope01 / Scope

Five highway authorities, 214 public sites and 37 legacy contracts had to converge on one network. The duct was designed around planned resurfacing so the corridor was only opened once.

  1. 01

    186 km of new duct across five local authority areas on a single planned corridor.

  2. 02

    1,900 km of fibre blown and spliced, connecting 214 public sites.

  3. 03

    Two core points of presence and 14 aggregation nodes with diverse routing.

  4. 04

    Managed telemetry and monitoring platform across schools, libraries, GP surgeries and council offices.

  5. 05

    Wayleave and traffic management coordination with five highway authorities.

  6. 06

    Migration of 214 sites away from 37 separate legacy connectivity contracts.

Award to handover

Single accountable project director

Cost reporting

Weekly cost-to-complete to client

Defects period

24 months with the delivery team

Key milestones02 / Programme

Award to final account,
in the order it happened.

Dates are as recorded in the programme and signed off at each progress meeting with the client's project manager.

  1. Mar 2024

    Award and corridor design

    Appointed by the combined authority. Six weeks of corridor design with five highway authorities aligned the duct route to planned resurfacing programmes.

  2. Jun 2024

    First point of presence live

    First core PoP energised three weeks ahead of programme, with 30 sites connected in the first month.

  3. Sep 2024

    100th site connected

    Half the estate migrated, with each site's legacy circuit kept live until the new service passed a 14-day stability test.

  4. Jan 2025

    All 214 sites live

    Schools, libraries, surgeries and council offices migrated to the new platform, and 37 legacy contracts exited.

  5. Feb 2025

    Handover and platform support

    Handed over three weeks early with 12 months of platform support and a published asset register for future works.

Social value breakdown03 / Social value

Priced at tender.
Reported quarterly.

For a digital programme the social value case rests on inclusion as much as employment. Both were contracted, measured and reported to the combined authority.

Contracted commitment

£0.8m

Digital inclusion
Free connectivity for 14 community hubs and 1,200 refurbished devices passed to residents.
£0.28m
Apprenticeships & skills
16 apprentices and a fibre-splicing academy run with the local further education college.
£0.22m
Local labour & supply chain
64% local labour, with £1.1m awarded to two regional build partners.
£0.18m
Carbon
Duct reuse across 41 km of corridor, avoiding an estimated 640 t CO₂e.
£0.12m
214
Public sites connected
186 km
Duct built
−3 wks
Programme variance
Next stepProcurement gateway

Bring us in at the
pre-market stage.

Tell us the scheme, the framework and the programme dates. A director responds to every enquiry within two working days, with a named point of contact for the bid.