A selection of schemes completed or in delivery across our three sectors. Values are final account unless marked otherwise; social value is measured against the authority's contracted baseline.
Full deck replacement and re-jointing across four slip roads, sequenced through 47 weekend possessions with no full carriageway closure. Off-site manufactured deck units took nine weeks out of the programme.
Public buildings53°48′12″N 001°32′41″W2023 — 2025£22.4m19 months
Northgate Acute Wing M&E
Acute NHS trust
Replacement of clinical ventilation, medical gas and theatre engineering services across a live acute wing. Fourteen decant moves sequenced around elective lists, with clinical commissioning signed off wing by wing.
4.2 km of strategic trunk main rehabilitated by trenchless lining through a floodplain site of special scientific interest, including eleven crossings of rail and river infrastructure in shared possessions.
186 km of new duct and 1,900 km of fibre connecting 214 public sites — schools, libraries, GP surgeries and council offices — onto a single managed telemetry and monitoring platform.
Tell us the scheme, the framework and the programme dates. A director responds to every enquiry within two working days, with a named point of contact for the bid.