Trent Valley Trunk Main
4.2 km of strategic trunk main rehabilitated by trenchless lining through a floodplain site of special scientific interest, including eleven crossings of rail and river infrastructure in shared possessions.
- Client
- Water undertaker, AMP8
- Contract value
- £16.8m
- Duration
- 14 months
- Programme
- 2024 — 2025
The main crosses a floodplain site of special scientific interest, so the asset was renewed from the inside. Trenchless lining kept excavation out of the floodplain and every crossing inside an existing possession.
- 01
4.2 km of 600–900 mm strategic trunk main rehabilitated by trenchless lining.
- 02
Eleven crossings of rail, river and strategic highway, all delivered inside shared possessions.
- 03
Four new valve installations and two pressure management chambers.
- 04
Telemetry and leak-detection instrumentation integrated into the undertaker's SCADA estate.
- 05
Habitat protection and reinstatement across 9.4 ha of floodplain SSSI.
- 06
Temporary supply arrangements maintained throughout, with no planned interruptions.
Award to handover
Single accountable project director
Cost reporting
Weekly cost-to-complete to client
Defects period
24 months with the delivery team
Award to final account,
in the order it happened.
Dates are as recorded in the programme and signed off at each progress meeting with the client's project manager.
Feb 2024
Award and environmental consents
Awarded under the AMP8 capital programme. Consents and protected-species mitigation were agreed with the environment regulator before mobilisation.
May 2024
First trenchless drive
First 480 m drive completed in nine days from existing access points, with no excavation in the floodplain.
Oct 2024
Rail and river crossings complete
All eleven crossings delivered in shared possessions, coordinated with two other programmes working the same corridor.
Feb 2025
Main recommissioned
Pressure tested, chlorinated and returned to service with no supply interruptions to the 38,000 properties on the network.
Apr 2025
Habitat reinstated and signed off
9.4 ha reinstated ahead of the establishment period, with the project ecologist's sign-off issued in April 2025.
Priced at tender.
Reported quarterly.
Environmental outcomes carry the same reporting weight as employment outcomes in the contract. Both are tracked monthly against the agreed baseline.
Contracted commitment
£1.2m
- Environment & biodiversity
- 9.4 ha of floodplain habitat reinstated, 1.2 km of new hedgerow, and a five-year monitoring commitment.
- £0.31m
- Apprenticeships & skills
- 19 apprentices, including six placements trained specifically in trenchless techniques.
- £0.38m
- Local labour & supply chain
- 72% local labour, with £1.8m spent with two regional civil engineering contractors.
- £0.34m
- Community resilience
- Three village flood-resilience schemes and a water-safety programme delivered in eight schools.
- £0.17m
- 4.2 km
- Trenchless length
- Zero
- Supply interruptions
- 9.4 ha
- Habitat reinstated