Programme record
Utilities52°57′19″N 001°09′02″W

Trent Valley Trunk Main

4.2 km of strategic trunk main rehabilitated by trenchless lining through a floodplain site of special scientific interest, including eleven crossings of rail and river infrastructure in shared possessions.

Client
Water undertaker, AMP8
Contract value
£16.8m
Duration
14 months
Programme
2024 — 2025
Project scope01 / Scope

The main crosses a floodplain site of special scientific interest, so the asset was renewed from the inside. Trenchless lining kept excavation out of the floodplain and every crossing inside an existing possession.

  1. 01

    4.2 km of 600–900 mm strategic trunk main rehabilitated by trenchless lining.

  2. 02

    Eleven crossings of rail, river and strategic highway, all delivered inside shared possessions.

  3. 03

    Four new valve installations and two pressure management chambers.

  4. 04

    Telemetry and leak-detection instrumentation integrated into the undertaker's SCADA estate.

  5. 05

    Habitat protection and reinstatement across 9.4 ha of floodplain SSSI.

  6. 06

    Temporary supply arrangements maintained throughout, with no planned interruptions.

Award to handover

Single accountable project director

Cost reporting

Weekly cost-to-complete to client

Defects period

24 months with the delivery team

Key milestones02 / Programme

Award to final account,
in the order it happened.

Dates are as recorded in the programme and signed off at each progress meeting with the client's project manager.

  1. Feb 2024

    Award and environmental consents

    Awarded under the AMP8 capital programme. Consents and protected-species mitigation were agreed with the environment regulator before mobilisation.

  2. May 2024

    First trenchless drive

    First 480 m drive completed in nine days from existing access points, with no excavation in the floodplain.

  3. Oct 2024

    Rail and river crossings complete

    All eleven crossings delivered in shared possessions, coordinated with two other programmes working the same corridor.

  4. Feb 2025

    Main recommissioned

    Pressure tested, chlorinated and returned to service with no supply interruptions to the 38,000 properties on the network.

  5. Apr 2025

    Habitat reinstated and signed off

    9.4 ha reinstated ahead of the establishment period, with the project ecologist's sign-off issued in April 2025.

Social value breakdown03 / Social value

Priced at tender.
Reported quarterly.

Environmental outcomes carry the same reporting weight as employment outcomes in the contract. Both are tracked monthly against the agreed baseline.

Contracted commitment

£1.2m

Environment & biodiversity
9.4 ha of floodplain habitat reinstated, 1.2 km of new hedgerow, and a five-year monitoring commitment.
£0.31m
Apprenticeships & skills
19 apprentices, including six placements trained specifically in trenchless techniques.
£0.38m
Local labour & supply chain
72% local labour, with £1.8m spent with two regional civil engineering contractors.
£0.34m
Community resilience
Three village flood-resilience schemes and a water-safety programme delivered in eight schools.
£0.17m
4.2 km
Trenchless length
Zero
Supply interruptions
9.4 ha
Habitat reinstated