Northgate Acute Wing M&E
Replacement of clinical ventilation, medical gas and theatre engineering services across a live acute wing. Fourteen decant moves sequenced around elective lists, with clinical commissioning signed off wing by wing.
- Client
- Acute NHS trust
- Contract value
- £22.4m
- Duration
- 19 months
- Programme
- 2023 — 2025
The wing stayed in clinical use throughout. Ventilation, medical gas and theatre engineering services were replaced ward by ward, with each handover signed off by the trust before the next decant began.
- 01
Replacement of clinical ventilation across six wards and three theatres, including AHU plant, ductwork and controls.
- 02
New medical gas manifold and distribution to HTM 02-01, with 214 terminal units re-commissioned.
- 03
Theatre engineering services: medical gas, UPS, isolated power and new theatre control panels.
- 04
Electrical resilience works — LV panel replacement, standby generator connections and protection grading.
- 05
Fourteen clinical decant moves sequenced around elective lists and cancer pathways.
- 06
Wing-by-wing commissioning with clinical and infection-prevention sign-off before each handover.
Award to handover
Single accountable project director
Cost reporting
Weekly cost-to-complete to client
Defects period
24 months with the delivery team
Award to final account,
in the order it happened.
Dates are as recorded in the programme and signed off at each progress meeting with the client's project manager.
Jan 2023
Award and clinical engagement
Awarded through a healthcare framework. Six weeks of ward-level engagement with matrons and infection prevention ran before any works started on site.
Jun 2023
First ward returned live
Ward seven handed back with new ventilation and no clinical downtime — the sequencing method repeated across the remaining five wards.
Feb 2024
Theatre three commissioned
Final theatre re-commissioned to HTM 03-01, with validation air tests witnessed and accepted by the trust's estates team.
Sep 2024
Medical gas infrastructure complete
New manifold and distribution live across the wing after 11 phased night-time changeovers, each with a documented purge and test.
Jul 2025
Handover and aftercare
O&M manuals, as-builts and a 24-month defects period, with a resident engineer on site for the first 12 months.
Priced at tender.
Reported quarterly.
Social value was scored at tender and contracted into the framework call-off. Reporting is quarterly, with outcomes verified by the trust rather than self-certified.
Contracted commitment
£1.9m
- Apprenticeships & skills
- 26 apprentices, plus 14 existing staff upskilled in healthcare ventilation and medical gas competence.
- £0.64m
- Local labour & supply chain
- 61% local labour, with £2.2m awarded to regional mechanical and electrical specialists.
- £0.48m
- Carbon & energy
- 31% reduction in wing energy use, measured over the first 12 months of operation.
- £0.52m
- Patients & community
- Two ward gardens, a clinical training fund and 340 hours of volunteered time from site staff.
- £0.26m
- Zero
- Clinical downtime
- 14
- Decant moves
- 31%
- Energy reduction
Bring us in at the