Programme record
Public buildings53°48′12″N 001°32′41″W

Northgate Acute Wing M&E

Replacement of clinical ventilation, medical gas and theatre engineering services across a live acute wing. Fourteen decant moves sequenced around elective lists, with clinical commissioning signed off wing by wing.

Client
Acute NHS trust
Contract value
£22.4m
Duration
19 months
Programme
2023 — 2025
Project scope01 / Scope

The wing stayed in clinical use throughout. Ventilation, medical gas and theatre engineering services were replaced ward by ward, with each handover signed off by the trust before the next decant began.

  1. 01

    Replacement of clinical ventilation across six wards and three theatres, including AHU plant, ductwork and controls.

  2. 02

    New medical gas manifold and distribution to HTM 02-01, with 214 terminal units re-commissioned.

  3. 03

    Theatre engineering services: medical gas, UPS, isolated power and new theatre control panels.

  4. 04

    Electrical resilience works — LV panel replacement, standby generator connections and protection grading.

  5. 05

    Fourteen clinical decant moves sequenced around elective lists and cancer pathways.

  6. 06

    Wing-by-wing commissioning with clinical and infection-prevention sign-off before each handover.

Award to handover

Single accountable project director

Cost reporting

Weekly cost-to-complete to client

Defects period

24 months with the delivery team

Key milestones02 / Programme

Award to final account,
in the order it happened.

Dates are as recorded in the programme and signed off at each progress meeting with the client's project manager.

  1. Jan 2023

    Award and clinical engagement

    Awarded through a healthcare framework. Six weeks of ward-level engagement with matrons and infection prevention ran before any works started on site.

  2. Jun 2023

    First ward returned live

    Ward seven handed back with new ventilation and no clinical downtime — the sequencing method repeated across the remaining five wards.

  3. Feb 2024

    Theatre three commissioned

    Final theatre re-commissioned to HTM 03-01, with validation air tests witnessed and accepted by the trust's estates team.

  4. Sep 2024

    Medical gas infrastructure complete

    New manifold and distribution live across the wing after 11 phased night-time changeovers, each with a documented purge and test.

  5. Jul 2025

    Handover and aftercare

    O&M manuals, as-builts and a 24-month defects period, with a resident engineer on site for the first 12 months.

Social value breakdown03 / Social value

Priced at tender.
Reported quarterly.

Social value was scored at tender and contracted into the framework call-off. Reporting is quarterly, with outcomes verified by the trust rather than self-certified.

Contracted commitment

£1.9m

Apprenticeships & skills
26 apprentices, plus 14 existing staff upskilled in healthcare ventilation and medical gas competence.
£0.64m
Local labour & supply chain
61% local labour, with £2.2m awarded to regional mechanical and electrical specialists.
£0.48m
Carbon & energy
31% reduction in wing energy use, measured over the first 12 months of operation.
£0.52m
Patients & community
Two ward gardens, a clinical training fund and 340 hours of volunteered time from site staff.
£0.26m
Zero
Clinical downtime
14
Decant moves
31%
Energy reduction