Programme record
Transport53°28′38″N 002°14′44″W

Larkfield Interchange Renewal

Full deck replacement and re-jointing across four slip roads, sequenced through 47 weekend possessions with no full carriageway closure. Off-site manufactured deck units took nine weeks out of the programme.

Client
Strategic road authority
Contract value
£48.0m
Duration
26 months
Programme
2022 — 2024
Project scope01 / Scope

Larkfield carries 74,000 vehicles a day between a strategic dual carriageway and a district distributor. Chloride-induced deterioration had taken all four slip-road decks past end of life. The brief was a structural renewal delivered without a single full carriageway closure.

  1. 01

    Structural deck replacement to four slip-road spans — 1,240 m² of deck and 96 expansion joints.

  2. 02

    Off-site manufacture of 26 deck units at our fabrication facility, trial-erected before first delivery.

  3. 03

    Bearing replacement, half-joint repair and cathodic protection to both approach substructures.

  4. 04

    Waterproofing, surfacing and vehicle restraint system to DMRB standard across 2.6 km.

  5. 05

    Drainage renewal and a new attenuation tank serving the southbound merge.

  6. 06

    Permanent traffic management, including 14 detector loops and two overhead gantries.

Award to handover

Single accountable project director

Cost reporting

Weekly cost-to-complete to client

Defects period

24 months with the delivery team

Key milestones02 / Programme

Award to final account,
in the order it happened.

Dates are as recorded in the programme and signed off at each progress meeting with the client's project manager.

  1. Mar 2022

    Award and early contractor involvement

    Called off a regional transport framework. Four weeks of buildability review moved the deck units to off-site manufacture and took nine weeks out of the programme before the first possession.

  2. Aug 2022

    First possession and deck lifting

    47 weekend possessions planned from the outset. The first deck unit was lifted with all four spans cast and trial-erected away from the network.

  3. Feb 2023

    Slip road two returned to traffic

    First completed span handed back 11 days ahead of programme, with temporary works removed inside the same possession.

  4. Nov 2023

    All decks installed

    Final unit lifted in the 38th possession. No possession overran, and 1,600 lane-nights were worked without a full carriageway closure.

  5. May 2024

    Handover and defects period

    As-built information and commissioning evidence issued at practical completion, with the 24-month defects period managed by the same project director.

Social value breakdown03 / Social value

Priced at tender.
Reported quarterly.

Committed at tender against the authority's PPN 06/20 baseline, priced into the contract sum and reported quarterly to the client's social value lead.

Contracted commitment

£3.4m

Apprenticeships & skills
42 apprentices across three intakes, with 11 moving into permanent roles in the delivery team.
£1.12m
Local labour & supply chain
68% of site hours worked by people living within 20 miles, and £4.1m spent with three local subcontractors.
£0.86m
Carbon & environment
3,100 t CO₂e avoided against baseline, largely through off-site manufacture and reusing 82% of arisings.
£0.79m
Community & education
18 school engagements, two community planting days and £40k contributed to a regional skills fund.
£0.63m
42
Apprenticeships
68%
Local labour
3,100 t
Carbon avoided